There were four Single-Family Home Applications reviewed by ARC in March. Two of these were recommended for approval, one was held for additional information, and one was cancelled by the contractor. Fifteen other applications were reviewed. Twelve were recommended for approval, two were held for additional information, and one unauthorized construction was recommended for fining.
Effective March 31, 2025, there were 64 new homes in the construction process.A total of 30 new homes have received Certificates of Occupancy this fiscal year (October 2024 to September 2025). Seven of these were received during the month of March.
The following architectural projects were either approved or conditionally approved by the Burnt Store Lakes Board of Directors during the March 11, 2025 Board Meeting: